24.04 Project Management Tools and Gantt - Quiz

Section 24.4 Quiz: Project Management Tools and Gantt

  1. What is the primary purpose of a Work Breakdown Structure (WBS)?

    • To calculate project costs
    • To break large projects into manageable tasks { data-correct }
    • To assign team members to specific roles
    • To track project expenses
  2. In a Gantt chart, what do the horizontal bars represent?

    • Project costs over time
    • Team member availability
    • Task duration and timing { data-correct }
    • Resource utilization rates
  3. What is the critical path in project management?

    • The most expensive sequence of tasks
    • The longest sequence of dependent tasks that determines project duration { data-correct }
    • The path with the most resources assigned
    • The sequence of tasks with the highest priority
  4. Which type of task dependency means “Task B cannot start until Task A finishes”?

    • Start-to-start
    • Finish-to-finish
    • Start-to-finish
    • Finish-to-start { data-correct }
  5. What is schedule variance (SV) in project tracking?

    • The difference between planned and actual costs
    • The difference between planned and actual progress { data-correct }
    • The number of tasks completed per day
    • The percentage of team members available
  6. Which project management tool would be MOST appropriate for a small agile development team?

    • Microsoft Project with detailed Gantt charts
    • Primavera P6 for enterprise planning
    • Trello with Kanban boards { data-correct }
    • Complex spreadsheet with formulas
  7. What does project velocity measure?

    • How fast team members work
    • The rate of project completion over time { data-correct }
    • The number of bugs found per day
    • The cost per task completed
  8. Which alert type should have the HIGHEST priority in project tracking?

    • A non-critical task running slightly behind schedule
    • A critical path task experiencing significant delays { data-correct }
    • A team member being 10% over their planned hours
    • A minor quality issue in completed work
  9. When evaluating project management tools, which factor is MOST important for a distributed team?

    • Advanced reporting capabilities
    • Low cost
    • Collaboration support { data-correct }
    • Complex scheduling features
  10. What is the main benefit of using milestones in project management?

    • They reduce project costs
    • They automatically assign resources
    • They provide clear checkpoints for progress assessment { data-correct }
    • They eliminate the need for task dependencies